Week 21 July 13

Finished removing all trees and bushes from the intersection of Lincoln and Franklin Rd. Worked on paper work for upcoming road work between the Townships on Erin Rd and Townline Rd Intersection. Continued the Second Cut on the Towns Roadsides. The Road work progress this week: Pulverization of Erin Rd from Lincoln to Townline Rd and Resthaven Rd from Harding north 830' or so up Resthaven Rd. The above road work is scheduled to be complete by the end of next week. Still no word from Scott Construction on the Warranty work to be done on Town MM - Adam Rd - and Oak St.